The dates below reflect the current expected delivery sequence and should be treated as the working project plan. Significant changes introduced after April 24, 2026 may affect these dates.
April 16, 2026
Provide initial project timeline and plan to Mike
Initial project timeline and plan delivered to Mike by EOD.
April 16, 2026
Opener attributes from Mike
Mike to provide the opener attribute structure to Jigx by end of day.
Monday, April 20, 2026
Screen flow + PRD to Mike
Updated screen flow and PRD delivered to Mike on Monday morning.
April 22, 2026
Open questions answered
All major design and integration questions answered through collaboration between Adriaan and Mike using a Microsoft Teams meeting or chat.
April 24, 2026
Test Acumatica restored
Current production environment restored into a test Acumatica instance for Jigx development and testing. Final attributes must also be loaded and ready for development.
April 27, 2026
Design reflected + final cost
Answered open items reflected in the design by Monday, April 27, with final development cost provided for acceptance. Credit to be applied for amounts already paid toward the Jigx sales solution.
May 15, 2026
First version available for testing
If design is signed off and inputs are delivered without major changes, first version available for Mike and others to test against the test Acumatica instance.
May 16–22, 2026
Fast followup revision + sign-off
Fast followup revisions available during the 7 days after first test release, with target final sign-off for field deployment by May 22.
May 25–29, 2026
Production move window
Planned move from test into production during the week of May 25 through May 29.
June 1, 2026
Target production readiness
Solution ready for full production use without the service sales component. Earlier deployment is possible if timelines are beaten.